NJ A5267
Bill
Status
8/22/2025
Primary Sponsor
Wayne DeAngelo
Click for details
AI Summary
-
Board of Public Utilities must establish a program to procure and provide incentive awards for transmission-scale energy storage systems (at least 5 MW AC capacity) interconnected with the PJM Transmission Network in New Jersey
-
Program requires procurement of at least 1,000 MW AC in installed capacity by June 30, 2026, with at least 350 MW AC approved in Tranche 1 by December 31, 2025 and remaining capacity in Tranche 2
-
Incentive awards consist of fixed annual payments over a 15-year award period, with eligible projects required to have anticipated commercial operations by December 31, 2030
-
Creates the "Energy Storage Fund" with minimum $60,000,000 annual deposits from societal benefits charges and other sources (including federal funding) to pay for incentive awards
-
Developers must provide pre-development security of up to $100,000 per megawatt (maximum $10,000,000 total) and meet performance requirements including minimum availability hours for dispatch
Legislative Description
Requires BPU to procure and incentivize transmission-scale energy storage.
Bills and Joint Resolutions Signed by the Governor
Last Action
Approved P.L.2025, c.136.
8/22/2025