NJ A4529
Bill
Status
3/9/2026
Primary Sponsor
Wayne DeAngelo
Click for details
AI Summary
-
Extends the deadline for New Jersey Board of Public Utilities to approve transmission-scale energy storage incentive awards from June 30, 2026 to December 31, 2026 for the 1,000 MW AC procurement goal.
-
Modifies Tranche 2 project maturity requirements to allow projects that are in the process of undergoing a Phase I System Impact Study through PJM, rather than requiring completed studies with Decision Point I Readiness Deposits.
-
Removes the requirement for Tranche 2 applicants to have paid a Decision Point I Readiness Deposit to PJM, expanding eligibility for incentive awards.
-
Maintains the existing Tranche 1 deadline of December 31, 2025 for approving at least 350 MW AC in incentive awards.
-
Amends P.L.2025, c.136, which established the BPU energy storage procurement program providing 15-year incentive awards for transmission-scale storage systems.
Legislative Description
Modifies certain requirements for transmission-scale energy storage procurement under BPU incentive program.
2nd Reading in the Assembly
Last Action
Reported out of Assembly Committee, 2nd Reading
3/16/2026