AI Summary

  • Allows construction of energy transmission and distribution infrastructure (not generation facilities) on preserved farmland in New Jersey with landowner approval
  • Requires components be placed within a 50-foot right-of-way as close as practical to the edge of preserved land, with underground installations at depths greater than 3 feet
  • Automatically permits projects meeting the specified criteria without State Agriculture Development Committee approval; non-compliant projects require committee application with 90-day review period
  • Development easement holders receive application copies and 30 days to comment; the committee can suspend or revoke approvals for violations
  • Projects in the Pinelands area must still comply with Pinelands Protection Act standards and the comprehensive management plan

Legislative Description

Authorizes construction, installation, and operation of certain energy project components on preserved farmland.

Withdrawn Because Approved

Last Action

Withdrawn Because Approved P.L.2025, c.390.

1/13/2026

Committee Referrals

Commerce and Economic Development1/13/2026

Full Bill Text