Entitlement applications (variances, zoning changes, special use permits) must receive a public hearing within 30 days of submission and a final decision within 90 days at county, township, and municipal levels
-
Zoning appeals boards must decide appeals within 30 calendar days after submission, replacing the previous "reasonable time" standard
-
Building departments must complete plan reviews and inspections within 30 days; if they fail to meet this deadline, contractors or owners may hire certified third-party private inspectors to perform the work
-
Subdivision plat approvals must be completed within 90 days (increased from 30 days), with automatic approval if no action is taken within that timeframe
-
Traffic studies for road access permits must be completed within 45 days of application, and local access management regulations cannot be stricter than corresponding state and federal standards