OK SB573
Bill
AI Summary
-
Reduces maximum retainage allowed in construction contracts from 10% to 5% of the payment due for both prime contractors and subcontractors.
-
Eliminates previous provision that reduced retainage to 5% only after prime contractor invoices reached 50% of contract value; now 5% cap applies immediately to all payment stages.
-
Requires owners to release retainage within 21 calendar days after certificate of substantial completion, minus costs to correct defective work (capped at 150% of estimated correction costs).
-
Mandates prime contractors release withheld funds to other entities within 10 calendar days of receipt, and requires all other entities to release their shares within 7 calendar days.
-
Declares an emergency, making the act effective immediately upon passage and approval.
Legislative Description
Public buildings and public works; relating to retainage of payments in certain construction contracts; reducing maximum percentage of retainage allowed in construction contracts. Emergency.
Business and Economic Development
Last Action
Approved by Governor 05/05/2010
5/6/2010