  • Establishes cumulative change order limits for public construction contracts: 15% for contracts of $1 million or less, and the greater of $150,000 or 10% for contracts exceeding $1 million.

  • Requires readvertising for bids on incomplete contract portions if change orders exceed the established limits in subsections A or B.

  • For agencies without governing bodies, authorizes the chief administrative officer to approve change orders; for state agencies, requires approval by the State Construction Administrator of the Department of Central Services.

  • Allows municipalities and technology centers to delegate approval authority for change orders up to $40,000 or 10% of the contract (whichever is less) to their chief administrative officer, with reporting to the governing body at the next meeting.

  • Becomes effective November 1, 2011.

Legislative Description

Public Competitive Bidding Act; modifying approval requirements for certain change orders. Effective date.

Government

Last Action

Approved by Governor 04/25/2011