PA SB991
Bill
Status
9/5/2025
Primary Sponsor
Camera Bartolotta
Click for details
AI Summary
-
Department of Environmental Protection must identify at least 15 preapproved data center sites within 90 days, with at least 5 located at decommissioned or soon-to-be-decommissioned power generation facilities
-
Creates a two-phase accelerated permitting process: Phase 1 requires a $10,000 fee and allows site preparation work within 3 days of application; Phase 2 requires final design and air quality permits at least 60 days before building construction begins
-
All permit applications must be certified by a Pennsylvania-licensed professional attesting compliance with applicable laws and regulations
-
Construction jobs at data center sites must pay prevailing wages to qualify for the accelerated permitting process
-
Program expires December 31, 2040, though projects already in the permitting process may continue after that date
Legislative Description
Providing for a permitting process for data center siting; and imposing powers and duties on the Department of Environmental Protection.
Last Action
Referred to Environmental Resources & Energy
9/5/2025