AI Summary
-
Prohibits RIPTA from using state funds or bond proceeds for any work performed after August 1, 2026, related to the "transit center joint development project" RFP issued in January 2023 or the preliminary services agreement executed in February 2024
-
Targets the proposed relocation of the Providence bus hub from Kennedy Plaza, which had a December 2022 cost estimate of $200-$250 million
-
RIPTA signed a preliminary services agreement in February 2024 paying a vendor up to $16.9 million for public communications, initial design, and site selection assistance
-
Legislative findings criticize the contract structure for allowing guaranteed profit margins with no enforceable maximum price, citing RIPTA's existing financial difficulties
-
Takes effect upon passage
Legislative Description
Prohibits RIPTA from using state funds or the proceeds of any bond(s) to pay for any work performed after 8/1/26, pursuant to the “transit center joint development project” RFP and/or pursuant to related the preliminary services agreement.
Public Utilities And Carriers
Last Action
Introduced, referred to Senate Finance
2/27/2026