AI Summary
-
Data center owners/operators must pay the full cost of infrastructure needed to support their facilities, including roads, water, wastewater, electric transmission lines, substations, and utility upgrades
-
Electric utilities are prohibited from raising rates for residential or other commercial/industrial customers due to increased electric demand caused by data centers
-
Electric utilities must create ratemaking structures ensuring all data center infrastructure and electric service costs are paid solely by the data center owner/operator
-
Before imposing any rate increase, electric utilities must make a written finding that the increase is not attributable to data centers and make that finding publicly available
-
Customers who believe a utility has violated these provisions may file complaints with the Tennessee Public Utility Commission or the utility's governing board; effective January 1, 2027
Legislative Description
AN ACT to amend Tennessee Code Annotated, Title 5; Title 6; Title 7; Title 13 and Title 65, relative to data centers.
Computers and Electronic Processing
Last Action
Action deferred in Senate Commerce and Labor Committee to 3/17/2026