TX HB3970

Bill

Status

Engrossed

5/1/2025

Primary Sponsor

Drew Darby

Click for details

Origin

House of Representatives

89th Legislature Regular Session

AI Summary

  • Requires the Public Utility Commission to establish an expedited interconnection process for large electrical loads in the ERCOT power region, giving queue priority to approved large loads over those without contractual agreements with utilities

  • Large loads can qualify for expedited processing by bringing behind-the-meter generation online within 180 days of interconnection that is registered with ERCOT and capable of serving the customer's full load requirement

  • Facilities with aggregated peak demand exceeding 75 megawatts can alternatively qualify by providing required data and financial security, and committing to operate as a "flexible load" for at least 10 years

  • Flexible loads must contractually agree to reduce consumption or switch to backup generation when directed by ERCOT or as needed to protect grid integrity during emergencies

  • Allows qualified large loads to contract with approved vendors to perform required interconnection studies and, with utility authorization, to procure equipment and construct interconnection facilities themselves

Legislative Description

Relating to the interconnection and operation of large loads.

Utilities

Last Action

Referred to Business & Commerce

5/15/2025

Committee Referrals

Business & Commerce5/15/2025
State Affairs3/27/2025

Full Bill Text

No bill text available