TX HB987
Bill
Status
11/12/2024
Primary Sponsor
Steve Toth
Click for details
AI Summary
-
Reduces the deadline for municipalities to grant or deny building permit applications from 45 days to 30 days after submission
-
Eliminates the previous option allowing municipalities to provide written notice explaining why they need more time to process an application (which had granted an additional 30-day extension)
-
Allows municipalities and applicants to reach a written agreement establishing an alternative deadline for permit decisions
-
Requires municipalities that fail to meet the 30-day deadline (or agreed-upon deadline) to refund all collected permit fees and prohibits them from collecting any fees for that application
-
Takes effect immediately with two-thirds legislative vote, otherwise September 1, 2025
Legislative Description
Relating to the time for issuance of a municipal building permit.
City Government
Last Action
Referred to Land & Resource Management
3/6/2025