TX HB993
Bill
Status
11/12/2024
Primary Sponsor
Steve Toth
Click for details
AI Summary
-
Requires municipalities to grant or deny building permit applications within 45 days, or provide written notice explaining the delay, or (for commercial permits only) reach a written agreement with the applicant on an extended deadline
-
Prohibits municipalities from denying a permit solely because they are unable to meet the processing timeline requirements
-
Prohibits municipalities from requiring applicants to waive the statutory processing time requirements
-
Mandates that municipalities forfeit permit fees and refund any fees already collected if they fail to comply with the processing timeline requirements
-
Applies only to permit applications submitted on or after September 1, 2025
Legislative Description
Relating to the time for processing a municipal building permit application.
City Government
Last Action
Placed on General State Calendar
5/13/2025