US HB8033
Bill
Status
3/20/2026
Primary Sponsor
Greg Landsman
Click for details
AI Summary
-
FERC gains sole authority 90 days after enactment to approve retail electricity rates charged to data centers with peak demand exceeding 50 megawatts, overriding traditional state jurisdiction over retail rates
-
Data center electricity rates must include full costs of constructing, upgrading, and expanding transmission, distribution, and generation facilities needed to interconnect data centers and maintain grid reliability
-
Electric utilities are prohibited from shifting data center-related infrastructure costs onto residential and small commercial customers through their retail rates
-
Violations of the data center provisions carry civil penalties of up to $10 million per day, significantly higher than standard Federal Power Act violations
-
Predispute nondisclosure clauses in data center construction contracts are unenforceable against elected public officials at federal, state, or local levels
-
EPA must contract with the National Academies to assess data center environmental and public health impacts—including noise, air pollution, water use, carbon emissions, and electronic waste—and submit findings within 180 days
Legislative Description
No Harm Data Centers Act
Last Action
Referred to the House Committee on Energy and Commerce.
3/20/2026