WA HB1819
Bill
Status
3/12/2025
Primary Sponsor
Stephanie Barnard
Click for details
AI Summary
-
Upgrading or rebuilding existing electric powerlines within existing rights-of-way becomes categorically exempt from State Environmental Policy Act (SEPA) review, including relocating small segments, widening rights-of-way to meet electrical standards, voltage increases, reconductoring, and adding utility poles
-
Exemptions do not apply when projects involve lands covered by water, or when a series of related actions together may have significant adverse environmental impact
-
Utilities must notify the Department of Archaeology and Historic Preservation and federally recognized Indian tribes with usual and accustomed areas before commencing exempt projects, with tribal consultation required to identify and protect archaeological, cultural, or tribal resources
-
Clean energy action plans must now include evaluation of where reconductoring would yield meaningful improvements to increase ampacity, reduce line loss, or improve grid resilience
-
Information provided by tribes regarding cultural resources must be kept confidential and exempt from public disclosure
Legislative Description
Increasing transmission capacity.
Last Action
House Rules "X" file.
2/19/2026