WI SB3
Bill
Status
1/24/2025
Primary Sponsor
Howard Marklein
Click for details
AI Summary
-
Solar and wind energy projects with a capacity of 15 megawatts or more must obtain approval from each city, village, and town where the project would be located before the Public Service Commission can issue construction certificates.
-
Municipalities must approve or disapprove projects by resolution within 90 days of receiving a request; failure to act within the deadline results in automatic approval.
-
Municipalities may extend the 90-day deadline by up to 90 additional days for reasons including needing more information (45 days), material modifications to the request (90 days), or other good cause.
-
Existing state law limitations on local restrictions of solar and wind energy systems do not apply to this new municipal approval process for projects 15 megawatts or larger.
-
The bill applies to both certificates of authority for public utility projects and certificates of public convenience and necessity for large electric generating facilities (100+ megawatts).
Legislative Description
Requiring local approval for certain wind and solar projects before Public Service Commission approval.
Last Action
Public hearing held
3/10/2026